Interventions in the flows of a river should be minimal. But this issue cannot be argued on the basis of the Indus Water Treaty, only on the basis of current concerns
Last February, the Court of Arbitration set up under the
Indus Waters Treaty (IWT), 1960, had given an interim award on the
Kishenganga dispute, allowing the diversion of waters from one tributary
of the Jhelum to another. It has now given the final award indicating
the extent of permissible diversion. In order to understand this fully,
it is necessary to go back to the Baglihar arbitration because some of
the issues that arose in that case find a sequel in the present one.
(Before
getting into the subject at hand, let me say that I have serious
reservations about the so-called run-of-the-river hydroelectric
projects. However, setting aside my own concerns, I am writing this
article strictly from the perspective of the IWT.)
In
the Baglihar Project, Pakistan had posed certain points of difference
on design and engineering matters, and the Neutral Expert (NE) had given
his findings on them. We need not go into those issues here but must
take note of two points on which Pakistan felt acute concern. First, the
NE had observed that the fact that the IWT was signed in 1960 did not
freeze all future projects to 1960 technology, and that state-of-the-art
technology can be adopted (that is a paraphrase, not an exact
quotation). Secondly, he had stressed the importance of proper
maintenance of the facilities built and advocated the periodical
‘drawdown’ flushing of the reservoir to get rid of sediment.
The
first statement that the IWT did not preclude the use of post-IWT
technological advances seemed eminently sensible and could not easily be
questioned, but Pakistani experts and scholars felt (rightly) that on
the same count it would also be justifiable to take into account other
new and emerging concerns. On the second point, namely the advocacy of
‘drawdown flushing’ of the reservoir, Pakistan felt that this amounted
to a major re-interpretation of the Indus Treaty and seriously
compromised the protection against being flooding provided to Pakistan
by the IWT.
They felt so strongly on this point that
they referred it to the Permanent Court of Arbitration (PCA) on the
Kishenganga project as a second issue along with the primary one of
diversion of waters from one tributary of the Jhelum to another. The PCA
accepted the Pakistani position on drawdown flushing; it observed that
India must find other answers to the sediment problem. A request from
India for a reconsideration or reinterpretation of that decision has now
been rejected by the PCA.
On the issue of how much
‘minimum’ or ‘environmental’ flow should be maintained in the
Kishenganga, both India and Pakistan had made detailed submissions to
the PCA. India had proposed the maintenance of a minimum flow of 4.25
cumec (cubic metres per second). Pakistan had argued that 20 to 40 cumec
would be needed. The PCA felt that the Indian analysis was inadequate
and that Pakistan’s study was much fuller and more elaborate. It made
its own calculations and tentatively arrived at a figure of 12 cumec.
Finally, it has mandated a minimum flow of 9 cumec.
A
detailed analysis of the decision by Himanshu Thakkar from SANDRP
(South Asian Network on Dams, Rivers and People) faults the PCA for its
flawed determination of the environmental flow (e-flow). That criticism
is entirely valid, but it must be remembered that the PCA was not a body
set up to determine environmental flows; it was an arbitral body set up
under the 1960 treaty to adjudicate a dispute between India and
Pakistan on the Kishenganga project in terms of the provisions of that
IWT.
Its decision on the permissible extent of
diversion of waters and the maintenance of a certain flow in the river
was, therefore, not a scientific determination of environmental flows
but an arbitral, dispute-settling decision: it accepts neither the
Indian position nor the Pakistani one but mandates an intermediate
position. In arriving at its compromise position, the PCA seems to have
been influenced by the consideration that hydroelectric power was
important; that the IWT permits run-of-the-river hydroelectric projects;
and that the viability of the 330-MW Indian project should not be
unduly disturbed.
A new variable
However,
an interesting question arises here. Determining e-flows was not within
the remit of the PCA as an arbitrator under the IWT or in terms of the
treaty; the concept was unknown in 1960 and does not figure in it. What
the IWT says is that if there is a diversion of waters from one
tributary of the Jhelum to another, existing uses on the former
tributary must be protected. Pakistan’s Neelum-Jhelum hydroeletric
project could not be treated as ‘existing use’ because work on it
started after India had commenced work on the Kishenganga project (as
determined by the PCA). Pakistan could have argued for existing
agricultural use but the PCA says that no data on this was submitted by
Pakistan. Evidently, Pakistan was unwilling to talk too much about
‘existing use’ for fear of appearing to accept implicitly the
inter-tributary diversion of waters. Instead, it argued for
environmental flows as this idea is now widely accepted.
Indeed
it is. No one will argue today against the proposition that a river
must flow and that interventions in flows should be minimal. However,
this issue cannot be argued on the basis of the 1960 treaty; it can only
be argued on the basis of current concerns. The PCA was fully justified
in taking note of those concerns, but this meant that it was going
beyond the treaty and dealing with issues not explicitly recognised in
it. But was this not precisely what the NE in the Baglihar arbitration
was doing when he advocated (a) state-of-the-art technology and (b)
drawdown flushing of the reservoir? (As a matter of fact, the IWT had
qualified its prohibition of outlets below the dead storage level by
allowing an exception where sediment control required this.) It was by
using the door partly opened by the NE that Pakistan was able to bring
in ideas of environmental flows, etc.
Now the wheel
has come full circle. The NE’s recommendation of drawdown flushing has
been overturned, but Pakistan’s argument for environmental flows has
been accepted.
Reinterpretating IWT
Let
me not be misunderstood. I am not questioning the need for e-flows.
They should be maintained not only on the Kishenganga but on all rivers,
including the eastern rivers that stand allocated to India. I am only
pointing out that the NEs in both the Baglihar case and the PCA in the
Kishenganga dispute were ‘reinterpreting’ the IWT, albeit in different
ways.
The decisions of the PCA are final and binding
and not appealable. The PCA has, however, provided for a review of the
e-flow determination by the Permanent Indus Commission after 7 years.
What
does this verdict mean for India and Pakistan? India can go ahead with
the Kishenganga project with some modifications to accommodate a minimum
flow of 9 cumec. Pakistan invoked the arbitration clause twice, but in
neither case was India obliged to abandon the project (Baglihar,
Kishenganga); it had to make only some minor changes. Pakistan might
have been disappointed at that outcome. However, Pakistan’s concern
about drawdown flushing has found an answer. Thus, both countries have
reason to be satisfied.
Let me conclude by returning
to my own concerns. Quite apart from Pakistani worries, may I ask as an
Indian: how many such projects is India going to build on the Jhelum and
the Chenab, and what will they do to those rivers and to the
mountainous areas? That is perhaps a naïve question, as a much larger
number of hydroelectric projects are being built or are proposed to be
built on other rivers (the Sutlej, the Ganga, and the Brahmaputra
system). Recent political developments clearly indicate that the
government (I do not distinguish between the UPA and NDA here) shares
the industry view that environmental concerns are a nuisance (I avoid
the adjective that usually accompanies that noun). However, why should
the government accept that nuisance and try to mitigate it by changing
the Minister? The better answer would be to blaze a trail
internationally by repealing the Environment Protection Act, 1986.
(The writer is a former Secretary, Water Resources, Government of India.)
Recent political developments indicate that the government shares the industry view that environmental concerns are a nuisance
It is truly a well-researched content and excellent wording. I got so engaged in this material that I couldn’t wait to read. I am impressed with your work and skill. Thanks. sediment control logs USA
ReplyDeleteWow, What an Excellent post. I really found this to much informative. It is what I was searching for. I would like to suggest you that please keep sharing such type of info.sediment control logs USA
ReplyDelete