Skip to main content

Centre gives six months to deal with cases of environmental clearance violations (downtoearth,)

The Ministry of Environment, Forest and Climate Change (MoEF&CC) has issued a notification, giving a six-month window period to project proponents, who have been operating without obtaining a prior environmental clearance (EC), to apply for the same. The notification, issued on March 14, clarifies that this opportunity can only be availed for projects or activities which are observed to be in violation till the date of the notification, thus, making this a one-time opportunity.

The Ministry says that the notification has been issued because it is “necessary to bring such projects and activities in compliance with the environmental laws at the earliest point of time, rather than leaving them unregulated and unchecked, which will be more damaging to the environment”. Thus, it is “essential” to grant EC to these projects with adequate safeguards to make them compliant.

What prompted such move?

The recent move comes in response to certain proposals that the ministry and the State Environment Impact Assessment Authorities (SEIAA) have been receiving from project developers for issuing “Terms of References” (ToR) and EC for projects which have “started the work on site, expanded the production beyond the limit of environmental clearance or changed the product mix without obtaining prior environmental clearance”.

Moreover, a decision of the National Green Tribunal (NGT) in July 2015 has prompted the government to take such step. The NGT, at that time, had quashed two office memoranda (dated December 12, 2012 and June 27, 2013) of the Union Environment Ministry that had laid down a process for granting EC to such cases of violation. Many project developers have been exploiting that. The tribunal considered those office memoranda to be “ultra vires”, because the granting of “ex post facto” EC frustrates the need of a prior EC as required under the Environment Impact Assessment (EIA) Notification, 2006.

Conditions of the latest notification for EC requirement and compliance

The latest notification lists a set of conditions that must be fulfilled by project developers for obtaining EC and for compliance of EC conditions.

The specifications that have been given for obtaining ECs include:

All applications of EC (for the violation cases), irrespective of their size and capacity, will only be appraised at the Central level by the respective sector-specific Expert Appraisal Committee (EAC).
The EAC will first examine whether the project or activity is at all a permissible activity at the site on which it has come up. If not, then closure will be recommended.
If the EAC considers the site to be agreeable, then the EAC will prescribe “specific ToR” for assessment of ecological damage; and developing remediation plan and Natural and Community Resource Augmentation Plan (NCRAP). This will be in addition to general ToR required under EIA Notification (2006) for EIA study or development of Environment Management Plan (EMP).
The remediation plan and/or the NCRAP shall be prepared by accredited consultants and will be an independent chapter in the EIA report.
The collection and analysis of data for assessment of ecological damage, preparation of remediation plan and NCRAP shall be done by an environmental laboratory duly notified under the Environment (Protection) Act (1986)—E(P)Act, or an environmental laboratory accredited by the National Accreditation Board for Testing and Calibration Laboratories or the Council of Scientific and Industrial Research (CSIR).
The EAC shall stipulate the implementation of EMP, comprising remediation plan and NCRAP corresponding to the ecological damage assessed and economic benefit derived due to violation as a specific condition of EC.
Specifications to ensure compliance

Besides laying out conditions for obtaining EC, the notification also gives certain specifications in order to ensure compliance of EC conditions and implementation of the remediation plan and the NCRAP. The one that’s particularly important is with respect to furnishing of bank guarantee.

The project proponent will have “to submit a bank guarantee equivalent to the amount of remediation plan and NCRAP with the State Pollution Control Board (SPCB)”. According to Manoj Kumar Singh, joint secretary, MoEF&CC, the bank guarantee should compel the project developers to implement the remediation plan and the NCRAP in a timely manner, because by not doing so, the bank guarantee will be forfeited or its renewal every time will cost the developer considerable additional money.

The notification also clarifies that the SPCBs will be able to take action under Section 19 of the E(P) Act for violation. This essentially means that that SPCB can file a complaint report on violation of the project developers, on the basis of which they can be taken to court. The concerned SPCBs will also not issue any consent to operate or occupancy certificate till the project is granted EC by the Centre.

Future concerns

While ideally an EC should not be granted once project activities have started, by the virtue of the EIA Notification (2006), but if it is now allowed even through a limited window, the implementation of remedial measures and compliance of clearance conditions must be strictly monitored. Compliance is a major concern, given the already poor monitoring and compliance status of EC conditions.

A clear timeframe for implementation of the remediation and augmentation plans is crucial. Also, the government must ensure compliance by specifying monitoring intervals and detailed reporting on the same. In all cases of non-compliance or improper implementation of remedial plans, the project proponent must be held for serious offence and should be held liable for stiff penalty.

Comments

Popular posts from this blog

NGT terminates chairmen of pollution control boards in 10 states (downtoearth,)

Cracking the whip on 10 State Pollution Control Boards (SPCBs) for ad-hoc appointments, the National Green Tribunal has ordered the termination of Chairpersons of these regulatory authorities. The concerned states are Himachal Pradesh, Sikkim, Tamil Nadu, Uttarakhand, Kerala, Rajasthan, Telangana, Haryana, Maharashtra and Manipur. The order was given last week by the principal bench of the NGT, chaired by Justice Swatanter Kumar. The recent order of June 8, 2017, comes as a follow-up to an NGT judgment given in August 2016. In that judgment, the NGT had issued directions on appointments of Chairmen and Member Secretaries of the SPCBs, emphasising on crucial roles they have in pollution control and abatement. It then specified required qualifications as well as tenure of the authorities. States were required to act on the orders within three months and frame Rules for appointment [See Box: Highlights of the NGT judgment of 2016 on criteria for SPCB chairperson appointment]. Having

High dose of Vitamin C and B3 can kill colon cancer cells: study (downtoearth)

In a first, a team of researchers has found that high doses of Vitamin C and niacin or Vitamin B3 can kill cancer stem cells. A study published in Cell Biology International showed the opposing effects of low and high dose of vitamin C and vitamin B3 on colon cancer stem cells. Led by Bipasha Bose and Sudheer Shenoy, the team found that while low doses (5-25 micromolar) of Vitamin C and B3 proliferate colon cancer stem cells, high doses (100 to 1,000 micromolar) killed cancer stem cells. Such high doses of vitamins can only be achieved through intravenous injections in colon cancer patients. The third leading cause of cancer deaths worldwide, colon cancer can be prevented by an intake of dietary fibre and lifestyle changes. While the next step of the researchers is to delineate the mechanisms involved in such opposing effects, they also hope to establish a therapeutic dose of Vitamin C and B3 for colon cancer stem cell therapy. “If the therapeutic dose gets validated under in vivo

SC asks Centre to strike a balance on Rohingya issue (.hindu)

Supreme Court orally indicates that the government should not deport Rohingya “now” as the Centre prevails over it to not record any such views in its formal order, citing “international ramifications”. The Supreme Court on Friday came close to ordering the government not to deport the Rohingya. It finally settled on merely observing that a balance should be struck between humanitarian concern for the community and the country's national security and economic interests. The court was hearing a bunch of petitions, one filed by persons within the Rohingya community, against a proposed move to deport over 40,000 Rohingya refugees. A three-judge Bench, led by Chief Justice of India Dipak Misra, began by orally indicating that the government should not deport Rohingya “now”, but the government prevailed on the court to not pass any formal order, citing “international ramifications”. With this, the status quo continues even though the court gave the community liberty to approach i